How is the margin requirement calculated?
Updated in 2024.10.15
The calculation formula is as follows: Margin requirement = Contract size × Volume (lot) ÷ Lev...
When are swap points reflected?
Updated in 2024.11.07
Swap is calculated at 20:00 GMT+0 in Winter and 21:00+1 in Summer except Saturdays and Sundays...
What is the freeze level?
Updated in 2024.11.05
At FXON, no freeze level is set for any products, allowing you to change or cancel orders at a...
What is the stop level?
Updated in 2024.12.18
At FXON, the stop level for all products is set to zero, enabling you to place limit or stop or...
How is the swap calculated?
Updated in 2024.11.05
The calculation formula is as follows: 1-Day Swap = Lot Size × Swap Points × Contract Size × D...